Heerema's Aegir vessel has safely completed the installation of the 4.000 mT jacket and topside for Qatargas' North Field Bravo Living Quarters Expansion project.

Aegir completes installation for Qatargas

The project itself was a historic milestone for Qatar, with the fabrication for the offshore living quarter expansion being done locally - a first for the nation. To mark such an important event in Qatar's energy story we are thrilled that Qatargas chose to utilize the Aegir to install their platform.

The Aegir firstly mobilized to Qatar's Ras Laffan Port where both structures were constructed by our client Rosetti Marino at the N-Kom yard. On February 14, the Aegir picked up the jacket horizontally from the quay side. The 1.000 mT structure was then sailed to the offshore site, upended, and positioned in a process that was first tested in Heerema's simulation center to ensure the safest and most efficient methods were used.

In the subsequent days the main piles, consisting of a leadsection and two ad-ons, were installed and driven to target penetration. Before the Aegir returned to the N-Kom yard to pick up the Qatar made topside on February 22, lifting the 3.000 mT structure from the quay side and setting it onto the Aegir deck. The next morning the Aegir set sail to the construction site, where the deck was successfully installed around midday. With both mobilizations being completed within 18 hours this was a significant and notable achievement for Heerema. 

The project was finalized on February 25, with both the jacket and topside safely installed by Heerema for Qatargas.

Source: Heerema