Allseas’ role in the second development phase for the Johan Sverdrup field is complete, concluding three years of planning and preparation with Equinor and partners.
Pioneering Spirit successfully installed the 95-m bridge connecting the newly installed P2 process platform to the neighboring riser platform on Monday.
It follows the safe single-lift installation of the 25,000 tonne P2 topsides last week.