Wednesday morning (Oct14), the FSRU vessel 'LNG CROATIA' sailed into the Viktor Lenac shipyard. 

FSRU LNG Croatia sailed into Viktor Lenac Shipyard

The FSRU vessel will remain in the shipyard until additional final tests of specific systems are carried out and which are expected to last up to 4 weeks. 

In accordance with the planned project activities, the arrival of the FSRU vessel at the location of the terminal is expected in early December this year, when all activities related to the commissioning of the terminal will begin, all in order for the terminal to start operating on 1st January 2021.

Source: LNG Croatia