Rambiz, Scaldis' heavy lift vessel, successfully installed the unmanned gas platform L13-FI for NAM.

The lifting, upending, positioning and driving of the monopile foundation was carried out using the Vibro Lifting Tool.

Spotted: Rambiz, Scaldis' heavy lift vessel, successfully installed the unmanned gas platform L13-FI for NAM

The verticality of the monopile was installed well within tolerance, without the use of a gripper frame or installation template. A vibro hammer drove the pile down to six meters before the target penetration, before an impact hammer completed the job. Scaldis then installed the column and topside.

Source: Scaldis