Yamal LNG announced that it has shipped its thirtieth million ton of LNG since the commencement of the project.
The Arc7 ice-class tanker “Nikolay Yevgenov” loaded the 411th cargo as the project reached 30 million tons of LNG dispatched since the start-up of Train 1 in December 2017.
The facility is currently exceeding the design capacity of 16.5 million tons per annum. In 2019, the first full year of simultaneous operation of all three liquefaction trains, Yamal LNG produced 18.4 million tons of LNG, exceeding the plant's design capacity by 11% or 1.9 million tons.
Source: Yamal